The Risti solar park in Lääne-Nigula municipality, western Estonia, was formally opened on 19 November 2026. With 244 megawatts of capacity, close to 340,000 panels and 270 hectares of land, it is the largest solar park in Estonia, according to ERR News. The developer, renewable energy company Sunly, says its expected annual output matches the electricity use of nearly 90,000 average Estonian households.

What has been built

Construction began in 2024, with Connecto as the main contractor. The panels sit on tracking systems that turn them from east to west through the day, according to Sunly's announcement. The €125 million project was developed with Metsagrupp and co-financed by the European Investment Bank, SEB and Luminor.

Because of the autumn weather, the ribbon was cut about ten kilometres away in Turba, in the building of the former Ellamaa power station, the local newspaper Lääne Elu reported. Its substation had already been connected to the network of grid operator Elering in September, EuroEnergy noted, citing Postimees.

The municipality has a direct stake. Under a local benefit arrangement, Sunly pays Lääne-Nigula 0.6% of the park's annual electricity sales revenue. Mayor Janno Randmaa welcomed those payments and the prospect of new technical jobs.

The limits behind the headline figure

The 244 MW figure is the panels' capacity, not what reaches the grid. The park can feed at most 184.5 MW into the network, the limit of its connection point. Output also depends heavily on the season: on the foggy, overcast day before the opening, Sunly chief executive Priit Lepasepp told Lääne Elu, the park was producing only around 5 to 10 MW.

ERR also reported a wider market problem. Estonia's installed solar capacity now exceeds its annual peak demand, and that has pushed summer midday power prices to zero. Lepasepp said standalone solar or wind farms are no longer viable, and the state-owned company Enefit has paused standalone solar projects. Sunly's answer at Risti is to add a 143 MW / 294 MWh battery storage system, built with Rolls-Royce and expected to start operating in 2027, plus a planned 42 MW wind farm and data centre capacity. Those later phases are plans, not completed work.

The household equivalent is the developer's estimate of expected annual production. It is not a measured result, and the park has not yet completed a full year of operation.